Q1 (16 Marks) Boilers & Steam 🔥 Repeated 6x in exams
MEKG • Written Exam

As second engineer onboard a tanker, describe the procedure for presenting a Main Boiler for survey by a classification society. (16)

Appeared In: Apr 2018Apr 2024Dec 2023Mar 2020Jun 2019Feb 2019

Verified Model Answer (Text Solution)

Structured for DG Shipping MEO Class II examination scoring criteria.

Exam Ready

As the second engineer onboard a tanker, presenting a main boiler for survey involves a detailed and structured approach to ensure all components are thoroughly inspected and maintained according to classification society standards. The following steps outline the procedure:


Planning:

  • Inform the classification society beforehand and decide on a suitable date and location for the survey.
  • Calculate the time required for the survey and ensure it fits within the available time frame.
  • Confirm that adequate manpower is available for the task.
  • Check for necessary spare parts and place orders to ensure timely delivery.
  • Arrange all required tools.
  • Review the boiler manual for specific procedures and special instructions.
  • Gather all past maintenance, inspection, and survey records.
  • Conduct a meeting with all personnel involved to discuss the work and procedures.
  • Perform any special checks required before shutting down the boiler.


Before stopping the boiler:

  • Inform the duty officer on the bridge about the commencement of work.
  • Switch over the boiler, main engine, and diesel generators to Low Sulphur Marine Gas Oil (LSMGO).
  • Perform a boiler soot blow to clean the boiler tubes.
  • Stop all auxiliary machinery that consumes steam.


Stopping the boiler:

  • Change the boiler to manual control.
  • Stop boiler firing and carry out post purging for at least five minutes.
  • Isolate the boiler.
  • Shut the main steam stop valve
  • When the boiler pressure drops to 3-4 bar, perform a scum blowdown to remove floating impurities.
  • Conduct a bottom blowdown to drain the water
  • Before the pressure drops to 2 bar open the vent valve.
  • Allow the boiler to cool down sufficiently.
  • Once the boiler is confirmed to be drained completely, carefully open the manhole door.


Precautions for entry:

  • Ventilate the boiler and check for oxygen and gas content.
  • Conduct a risk assessment and follow safe entry procedures as per the company's Safety Management System (SMS).
  • Prepare an enclosed space entry permit and obtain signatures from all concerned parties.


Inspection:

Boiler Cleaning:

  • Thoroughly clean the boiler on water side, fire side and refractory.


Inspection on Gas side and refractory:

  • Check the condition of refractory material for any damage and cracks
  • Check for high temperature cracks in front of burner i.e. the back wall of furnace
  • Check the floor for any cracks and oil contamination
  • Check for signs of overheating near burner surface
  • Check for leaks at boiler tube at the plate entry
  • Check for carbon deposits/ soot deposits
  • Check for restriction of gas passage
  • Check the soot blower nozzle.
  • Examine the condition of tubes.
  • Check the exterior for corrosion, leakage, cracks, and overheating.
  • Inspect the condition of insulation, pipes, valves, refractory, and burning equipment.


Waterside Inspection:

  • Check the internal condition for scale, sludge and corrosion
  • Check the bottom blow-down and scum blow-down pipe from the inside of the boiler for any signs of erosion
  • Check for any distortion of boiler bottom plate
  • Check for steam bubbling pitting on tubes and wall
  • Check for oxygen pitting at waterline and steam space
  • Check condition of manhole door, mudhole/ handhole door from the inside of boiler.
  • Examine pipelines and valves.


External inspection:

  • Check the condtion of boiler support (top bracing)
  • Remove insulation and check for corrosion
  • Check boiler mounting attachment to the shell
  • Check the condition of boiler gauge glass connection
  • Check for any leaks from steam gasket


Additional Inspections:

  • Overhaul and inspect all boiler mountings.
  • Inspect and overhaul safety valves.
  • Calibrate pressure gauges.
  • Check the condition of Forced Draft (FD) fans, dampers, and linkages.
  • Inspect foundation bolts for tightness, corrosion, and fretting.
  • Inspect the uptake.
  • Measure tube thickness.


Post inspection:

  • Reassemble the boiler and follow the proper procedure for firing it up.
  • Test and set the safety valve.
  • Test all alarms and trips.
  • Prepare detailed measurement and inspection reports.
  • Ensure all reports are signed by the classification surveyor.


Prepare three copies of the report, duly signed by the classification surveyor:

  • One copy is retained by the surveyor.
  • One copy is sent to the company.
  • One copy is placed in the ship survey file.