Q2 (16 Marks) Lubrication & Bearings
MEP • Written Exam

(a) Describe how an auxiliary boiler would be blown down and opened up for inspection.

(b) State the Precautions which should be taken during the inspection and when boxing up the boiler for service.

(c) Which parts require particularly close attention when opened up and describe the procedure for the setting of safety valves.

Appeared In: Mar 2024

Verified Model Answer (Text Solution)

Structured for DG Shipping MEO Class II examination scoring criteria.

Exam Ready
Part (a)

BLOWING DOWN AND OPENING UP AN AUXILIARY BOILER FOR INSPECTION

  1. Preparation: Inform the watch/ duty engineer, obtain permission, and prepare a permit-to-work/ risk assessment. Stop the boiler firing and allow it to cool and depressurise.
  2. Blow down: Open the bottom blowdown valve (and surface blowdown as required) to discharge sludge and concentrated boiler water to the blowdown tank/ overboard (in accordance with MARPOL/ local regulations - blowdown water must not be discharged overboard in port/ restricted areas). Blow down until the boiler is empty/ drained as required.
  3. Isolate: Close and secure the steam, feed water, fuel and air connections; blank off or lock the valves; tag the boiler "not to be fired".
  4. Vent and cool: Open the vents/ manhole to allow the boiler to cool and the atmosphere to be safe; ventilate thoroughly.
  5. Open up: Remove the manhole covers (top and bottom) and the inspection/ handhole covers to give access to the steam space, water space, tubes, drum and headers.
  6. Clean: Remove sludge, scale and deposits from the water side; clean the fire side (tubes, furnace) of soot and deposits.
  7. Inspect: Carry out the internal and external inspection (see part c).
Part (b)

PRECAUTIONS DURING INSPECTION AND WHEN BOXING UP

During inspection:

  • Ensure the boiler is isolated, cooled, vented and gas-free; test the atmosphere before entry (enclosed-space entry permit).
  • Use correct PPE and follow the enclosed-space entry procedure (stand-by watch, lifeline, communication).
  • Do not enter until the boiler is safe (cool, no pressure, no toxic/ flammable gas).
  • Use adequate lighting (approved, low-voltage) and tools.
  • Protect the boiler internals from damage.

When boxing up:

  • Ensure all personnel are out and all tools/ materials are removed from the boiler.
  • Clean and inspect the manhole/ handhole faces and fit new gaskets.
  • Refit and torque the manhole covers correctly (in the correct sequence).
  • Close all vents, drains and openings.
  • Refill the boiler with treated feed water to the correct level.
  • Carry out a hydraulic/ steam test as required before returning to service.
  • Reconnect the steam, feed, fuel and air connections and remove the blanks/ locks.
  • Bring the boiler back on line gradually, checking for leaks and correct operation.
Part (c)

PARTS REQUIRING CLOSE ATTENTION AND SETTING OF SAFETY VALVES

Parts requiring close attention:

  • The water side: tubes, tube plates, drum, headers, for corrosion, pitting, scale, cracking and wastage.
  • The fire side: tubes, furnace, for soot, corrosion, erosion and cracking.
  • The manhole/ handhole faces and gaskets.
  • The safety valves, water level controls, and the feed water system.
  • The boiler shell/ drum for corrosion, cracking and distortion.

Setting of safety valves:

  • The safety valves are set to lift at the correct pressure (the boiler's working pressure, or as per Class requirements - typically set to lift at the working pressure and to reseat at a set blowdown).
  • Procedure: With the boiler at operating pressure (or using a test/ gagging arrangement), the safety valve spring/ setting is adjusted so the valve lifts at the set pressure. The valve is tested by raising the boiler pressure (or by a test rig) and observing the lift and reseat. The setting is verified and recorded, and the valve is sealed/ locked to prevent tampering. The safety valve must be set to comply with the classification society requirements (e.g. lift at working pressure, reseat within a set blowdown, and have adequate capacity).