Q6 (16 Marks) Engine Operation & Maintenance
MEP • Written Exam

One of the F.O. Storage tank in the engine room is due for survey by classification society.

Keeping in mind the safety of personnel, Enlist the procedure you will follow, to prepare the same for internal examination. (16)

Appeared In: Mar 2026

Verified Model Answer (Text Solution)

Structured for DG Shipping MEO Class II examination scoring criteria.

Exam Ready

PREPARING AN F.O. STORAGE TANK FOR INTERNAL EXAMINATION (SURVEY)

Keeping safety of personnel paramount, the tank is gas-freed and made safe before entry under the requirements of the code of safe working practices and MARPOL (for oil residue) and the company's enclosed-space entry procedure.

Procedure

  1. Pre-job planning and risk assessment: Identify the tank, inform the watch/ duty engineer, prepare a written risk assessment and a permit-to-work / enclosed space entry permit; brief all personnel, appoint a responsible officer in charge and a competent entry team/ stand-by watch.
  2. Check tank contents and position: Confirm which F.O. storage tank, its capacity, contents (heavy fuel oil/ intermediate), and plan the transfer.
  3. Empty the tank: Transfer the fuel out to another storage tank or settling tank using the transfer pumps, working through the sounding/ vent. Take care not to overfill the receiving tank; monitor soundings. Do not discharge any oil overboard (MARPOL reg 12); arrange for any sludge/ residue to be kept in a slop/ oily water system or to a reception facility.
  4. Isolate the tank: Close and secure the suction valve (from the tank to the service system) and any filling/overflow/ vent valves connecting to the bunker system; lock off or blank them, and tag the valves with "isolated for tank entry".
  5. Clean the tank: Drain as much as possible. Then, using appropriate means, remove sludge and residue; where possible, wash with hot fresh water (or use an approved tank-washing/ cleaning arrangement to a slop tank), and heat the tank (by steam coils/ heating) to lower viscosity and aid stripping. Remove deposits and scale. Where required, use the tank stripping/ evacuation means to a slop tank; never discharge residue overboard.
  6. Gas-free (ventilate) and test the atmosphere: Connect the tank ventilation/ opening; ventilate thoroughly (mechanical ventilation/ natural) until the monitored atmosphere is safe. Before entry, test the tank atmosphere using an approved gas detector for: oxygen (O2 20.9% normal, min 19.5%); flammability (lower explosive limit - below 1% of LFL, i.e. essentially no flammable vapour); and toxic gases (hydrogen sulphide, carbon monoxide, hydrocarbon vapour). Re-test at set intervals.
  7. Enclosed-space entry permit: Complete and sign the enclosed space entry permit; maintain a competent watch outside at all times, with a means of communication; provide for rescue/ emergency arrangements and a first-aid/ rescue plan; use a lifeline/ harness and a personal monitor where required.
  8. Perform the internal examination: The surveyor/ attending engineer enters to carry out the internal examination - visual inspection of internals (stiffeners, tank top/ bottom, bulkheads, suction, coils, condition of coatings), thickness measurement (UTM) where required, and check for corrosion, pitting, cracks, and condition of the tank. Take representative test readings/ samples as required. Only personnel certified/ trained for enclosed space entry enter; obey time limits and continuous monitoring.
  9. Withdraw and re-commission: When complete, all personnel exit, the manhole is closed and re-secured, the tank is re-vented/ purged as required for fuel service, and the suction/ vents are un-isolated and the tank re-pressurised/ refilled; carry out a leak/ stand test where needed.
  10. Record: Complete the entry log, permit closure, and the survey record; retain findings for the classification report.