Launch Interactive Practice Room In addition to a pressure gage and a relief valve, an air receiver should be fitted with a __________.
A
sight glass and manhole
B
thermometer and sight glass
C
thermometer and manhole
D
drain connection
✓ Correct Answer
USCG NMC Regulatory Explanation
In USCG Marine Engineering General Subjects, for engine room systems involving 'In addition to a pressure gage and a relief valve, an air receiver should be fitted with a', the standard operating requirement is: 'drain connection'.