USCG USCG Steam
Set 13 • Question #137 of 496
Launch Interactive Practice Room The turbo generator steam stop is located between the superheater outlet and the main steam stop valve to __________.
A
provide for easier access
B
provide higher quality steam for the turbo generators
C
provide a flow of cooling steam through the control desuperheater
D
allow the use of superheated steam in the turbo generator without pressurizing the larger main steam line
✓ Correct Answer
USCG NMC Regulatory Explanation
In USCG Steam Plants (Boilers & Turbines), regarding 'The turbo generator steam stop is located between the superheater outlet and the main steam stop valve to', the verified engineering fact is: 'allow the use of superheated steam in the turbo generator without pressurizing the larger main steam line'.
Question Discussion & Notes
0Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.
Loading mariner discussions...