Benchmark: 70% Standard: USCG NMC / 46 CFR
USCG USCG Steam Set 14 • Question #165 of 496
Launch Interactive Practice Room

A boiler is to be secured in port. After the burners have been secured, the forced draft fan and air registers should be secured __________.

A
immediately after carrying out the former procedures ✓ Correct Answer
B
after any oil on the furnace floor has been burned off and cleared of combustion gases
C
after 30 minutes has elapsed, after carrying out these procedures
D
after at least 1 hour has elapsed, after carrying out these securing procedures