USCG USCG Steam Set 2 • Question #258 of 496
Launch Interactive Practice Room

If a vessel is steaming at a steady rate, and the water level has dropped out of sight in the boiler gage glass, the FIRST corrective action should be to __________.

A
open the feedwater bypass regulator
B
blowdown the boiler gage glass
C
slow down the engines
D
cut out the fires ✓ Correct Answer