USCG USCG Steam
Set 5 • Question #362 of 496
Launch Interactive Practice Room Serious tube leaks in the air ejector condenser assembly will cause __________.
A
clogged steam strainers
B
fouled nozzles
C
loss of vacuum
✓ Correct Answer
D
faulty steam pressure
USCG NMC Regulatory Explanation
In USCG Steam Plants (Boilers & Turbines), regarding 'Serious tube leaks in the air ejector condenser assembly will cause', the verified engineering fact is: 'loss of vacuum'.
Question Discussion & Notes
0Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.