A water-tube boiler can be laid up either wet or dry. If it is to be laid up wet, you should __________.
Official USCG Answer & Rule Citation
Correct Answer: Option C — completely fill the boiler with deaerated feed water and maintain a slight pressure
Wet layups require filling the boiler completely with chemically treated, deaerated feedwater and maintaining a slight positive head pressure to prevent oxygen ingress and subsequent pitting corrosion.