As a chief engineer, which of the following instructions would be most appropriately entered into the Chief Engineer's night orders due to the non-routine nature of the instruction?
Official USCG Answer & Rule Citation
Correct Answer: Option B — The officer in charge of the engineering watch shall notify the chief engineer without delay when No.2 SSDG repairs are complete and the generator has been prepared for testing.
Under USCG National Maritime Center examination standards, the accepted correct answer is: The officer in charge of the engineering watch shall notify the chief engineer without delay when No.2 SSDG repairs are complete and the generator has been prepared for testing..
100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.