Deck General USCG Question #5094 (Set 158)

For planning purposes, the time required to place the DEEP DRILLER at survival draft from the drilling mode to counter heavy weather is __________.

Official USCG Answer & Rule Citation

Correct Answer: Option C — 6 hours

Standard operating procedures and the operations manual for the DEEP DRILLER specify a mandatory 6-hour operational planning window to transition the unit safely from active drilling mode to survival draft during heavy weather approaches.

100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.
Back to Deck General Sets