Deck General USCG Question #3553 (Set 113)

How often must the emergency generator be tested on a mobile offshore drilling unit?

Official USCG Answer & Rule Citation

Correct Answer: Option C — Once each month

Title 46 CFR mandates that emergency generators on Mobile Offshore Drilling Units (MODUs) undergo operational testing at least once each month to ensure reliability and immediate availability during a primary power failure or critical emergency scenario.

100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.
Back to Deck General Sets