If a ship is to be laid up for an indefinite period, the steam side of the main condenser should be __________.
Official USCG Answer & Rule Citation
Correct Answer: Option C — completely drained of water
When laying up a marine steam plant indefinitely, the main condenser steam side must be completely drained and dried to prevent galvanic corrosion, crevice corrosion, and pitting of tube sheets and shell internals as per standard marine preservation practices.