In a closed-loop process control system, what term is used to describe the action of measuring the difference between the actual result and the desired result and using that difference to drive the actual result toward the desired result?
Official USCG Answer & Rule Citation
Correct Answer: Option C — Feedback
Under USCG National Maritime Center examination standards, the accepted correct answer is: Feedback.