Steam Plants (Boilers & Turbines) USCG Question #335 (Set 12)

In order to maintain the effectiveness of the lube oil centrifuge to remove water, the engineer in charge should __________.

Official USCG Answer & Rule Citation

Correct Answer: Option C — take lube oil samples each week and place in clear containers for inspection

Routine visual inspection of lube oil samples drawn weekly into clear containers is the standard shipboard method to verify purifier efficacy and detect emulsified water or free moisture early.