"Line Displacement" is a procedure that is followed at an oil terminal facility, when there is a change of which of the following?
Official USCG Answer & Rule Citation
Correct Answer: Option A — product during the final phase of loading
Line displacement is the process of pushing the remaining cargo in the shore or ship lines into the tank using a different product or a pig. This is performed during the final phase of loading to ensure that the entire quantity of the intended product reaches the tank.