On a tank vessel, when must each high level alarm and tank overfill alarm must be tested?

Official USCG Answer & Rule Citation

Correct Answer: Option C — no earlier than 24 hours prior to loading

USCG marine safety regulations mandate that high-level and overfill alarms on tank vessels must be operationally tested no earlier than 24 hours prior to commencing cargo transfer to guarantee critical pollution prevention systems function properly.