Payment of penalty for a ship's delay after the expiration of lay days due to some fault of the charterer or his agent is known as __________.
Official USCG Answer & Rule Citation
Correct Answer: Option B — demurrage
In maritime charter parties, demurrage is the agreed-upon liquidated damages paid by the charterer to the shipowner for delaying the vessel in loading or discharging cargo beyond the stipulated time, known as lay days.