Steam Plants (Boilers & Turbines) USCG Question #405 (Set 14)

Precautions to be observed prior to starting a turbine driven cargo pump, should include __________.

Official USCG Answer & Rule Citation

Correct Answer: Option B — checking the manual trip device for proper operation

Operational testing of the manual trip device verifies the mechanical linkage and trip valve freedom of movement before placing a steam turbine in service, ensuring rapid emergency shutdown capability under 46 CFR requirements for auxiliary machinery.