Steam Plants (Boilers & Turbines) USCG Question #722 (Set 25)

Prior to rolling the main turbines in preparation for getting underway, you should __________.

Official USCG Answer & Rule Citation

Correct Answer: Option D — disengage the turning gear

Disengaging the turning gear is a mandatory interlock check before rolling the main turbines to prevent catastrophic mechanical destruction of the reduction gears and turning gear drive components.