Deck General USCG Question #5193 (Set 161)

Sea water temporarily pumped into tanks to simulate the increased vertical loading of environmental forces is termed __________.

Official USCG Answer & Rule Citation

Correct Answer: Option D — preload

Preload operations utilize temporary ballasting, often pumped into dedicated preload tanks, to simulate extreme environmental overturning moments and seat the spudcans into the seabed prior to elevating the main hull above the wave action.