Deck General USCG Question #2464 (Set 78)

The annual survey for endorsement of a Load Line Certificate must be held within __________.

Official USCG Answer & Rule Citation

Correct Answer: Option C — three months either way of the certificate's anniversary date

International Load Line regulations mandate that annual surveys for endorsement of a Load Line Certificate must be completed within a three-month window either way (before or after) the specific anniversary date of the certificate's issuance.