The DEEP DRILLER is loaded as shown in the Sample Load Form #3 (Preparing to Drill). If the liquid mud in mud pit #1 (see table 8) is dumped, what would be the new draft?
Official USCG Answer & Rule Citation
Correct Answer: Option C — 59 feet 2.7 inches
Under USCG National Maritime Center examination standards, the accepted correct answer is: 59 feet 2.7 inches.