Deck General USCG Question #4455 (Set 143)

The DEEP DRILLER is loaded as shown in the Sample Load Form Number 5 (Survival) when an unexpected slowly increasing starboard list and bow down trim occurs. A leak in 1S is found. By deballasting from ballast tanks 2S and 3S, the inclination slowly decreases. The increase in the transverse free surface corrections is __________.

Official USCG Answer & Rule Citation

Correct Answer: Option D — 0.22 foot

Under USCG National Maritime Center examination standards, the accepted correct answer is: 0.22 foot.

100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.
Back to Deck General Sets