Deck General USCG Question #4231 (Set 135)

The DEEP DRILLER, while loaded as shown in the Sample Load Form #4 (Drilling), suffers damage to the starboard forward column below the waterline. Pumping from tank 2S and 3S is not sufficient to prevent increasing starboard list and bow down trim. You should consider counterflooding in tank __________.

Official USCG Answer & Rule Citation

Correct Answer: Option C — 10P

Under USCG National Maritime Center examination standards, the accepted correct answer is: 10P.