The emergency power system for the DEEP DRILLER should be placed in operation when the weather forecast predicts winds greater than 90 knots and when __________.

Official USCG Answer & Rule Citation

Correct Answer: Option B — evacuating the unit

MODU emergency preparedness manuals require emergency power systems to be placed online ahead of severe environmental threats (winds over 90 knots) specifically when initiating personnel evacuation procedures to ensure continuous safety systems power.