Deck General USCG Question #3420 (Set 109)

The initial tension set in the mooring system of a MODU establishes the __________.

Official USCG Answer & Rule Citation

Correct Answer: Option C — distance the unit can be offset from the wellbore before the restoring forces oppose the environmental forces

Initial mooring line pretension dictates the dead band or offset distance a MODU can experience before environmental forces overcome the restoring forces and cause significant horizontal displacement from the wellbore.