Deck General USCG Question #3447 (Set 110)

The primary purpose for using stud link chain in a mooring system on a rig is the __________.

Official USCG Answer & Rule Citation

Correct Answer: Option B — stud keeps the chain from kinking

Under USCG National Maritime Center examination standards, the accepted correct answer is: stud keeps the chain from kinking.

100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.