What is the Inert gas plant on an LNG vessel designed to produce?
Official USCG Answer & Rule Citation
Correct Answer: Option C — inert gas and dry air with a minimum dew point of -40°F
LNG vessel inert gas plants must produce high-quality inert gas and dry air with a dew point of -40°F (-40°C) or lower. This extreme dryness prevents moisture condensation and freezing within the cryogenic cargo system, which could otherwise damage valves and piping.