What project management scheduling chart is a bar chart with the activity or task descriptions displayed on the left and listed vertically from top to bottom, and the calendar displayed on the top and laid out horizontally from left to right?
Official USCG Answer & Rule Citation
Correct Answer: Option B — Gantt chart
A Gantt chart maps project tasks vertically on the left against a horizontal calendar timeline, providing a clear visual representation of schedule duration and progress.