What shall the transfer procedures required to be followed on tankships contain?
Official USCG Answer & Rule Citation
Correct Answer: Option B — a line diagram of the vessel transfer piping
Title 33 CFR mandates that tankship transfer procedures include a clear, legible line diagram of the vessel's entire cargo piping system, showing valves, pumps, vent lines, and deck connections to facilitate rapid response during normal operations or emergencies.