Deck General USCG Question #2571 (Set 81)

What shall the transfer procedures required to be followed on tankships contain?

Official USCG Answer & Rule Citation

Correct Answer: Option B — a line diagram of the vessel transfer piping

Title 33 CFR mandates that tankship transfer procedures include a clear, legible line diagram of the vessel's entire cargo piping system, showing valves, pumps, vent lines, and deck connections to facilitate rapid response during normal operations or emergencies.