When a combination chain and wire rope mooring line is used, the chain is deployed __________.
Official USCG Answer & Rule Citation
Correct Answer: Option A — at the anchor end of the line
Deploying heavy chain at the anchor end provides essential catenary weight on the seabed, improving the anchor's holding angle and absorbing dynamic shock loads.