Steam Plants (Boilers & Turbines) USCG Question #9 (Set 1)

When starting a turbo generator in an automated plant, you must provide lube oil pressure to the unit by means of __________.

Official USCG Answer & Rule Citation

Correct Answer: Option A — the hand operated or auxiliary lube oil pump

Automated plant auxiliary turbo generators require pre-lubrication before startup to protect high-speed bearings. Operators must manually operate the auxiliary or hand lube oil pump to establish required oil pressure prior to rolling the turbine.