Deck General USCG Question #4488 (Set 144)

While at operating draft, the DEEP DRILLER suffers flooding in the port pump room. Both port bilge pumps are inadequate to dewater the pump room. You may supplement the bilge pumps with the __________.

Official USCG Answer & Rule Citation

Correct Answer: Option C — port drill water pump

Under USCG National Maritime Center examination standards, the accepted correct answer is: port drill water pump.

100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.
Back to Deck General Sets