While off-loading from an offshore supply vessel with the crane, the wind increases in strength and changes direction significantly, you should __________.
Official USCG Answer & Rule Citation
Correct Answer: Option D — move the offshore supply vessel to the downwind side
Under USCG National Maritime Center examination standards, the accepted correct answer is: move the offshore supply vessel to the downwind side.