General Subjects (Auxiliaries & Systems) USCG Question #2268 (Set 35)

You are the relieving the Chief Engineer of a general cargo vessel of more than 1600 gross tons on an international voyage. You have just signed on the vessel and after reviewing the machinery running hours you notice the Emergency Generator has not been run in over sixty days. How would you proceed?

Official USCG Answer & Rule Citation

Correct Answer: Option A — During your next port stay arrange with the Captain to run the Emergency Generator under load for at least two hours.

Under USCG National Maritime Center examination standards, the accepted correct answer is: During your next port stay arrange with the Captain to run the Emergency Generator under load for at least two hours..