Benchmark: 70% Standard: USCG NMC / 46 CFR
USCG USCG Motor Set 7 • Question #296 of 382
Launch Interactive Practice Room

In readying an auxiliary water-tube boiler for a routine hydrostatic test, which of the following procedures should be undertaken prior to filling the boiler with fresh water?

A
The safety valve escape piping should be disconnected from the valve body and a blank inserted.
B
The boiler vent valves should be opened. ✓ Correct Answer
C
All handhole/manhole covers should be tightened up as much as possible to preclude any leaks.
D
All of the above.