Benchmark: 70% Standard: USCG NMC / 46 CFR
USCG USCG Motor Set 8 • Question #338 of 382
Launch Interactive Practice Room

When an auxiliary boiler is secured and you expect to relight the unit within six hours, you should____________.

A
maintain a head of steam not less than 10 psig ✓ Correct Answer
B
completely fill the boiler with feedwater
C
flush the boiler and close the waterside airtight
D
maintain steam pressure 10 psig below normal boiler load.

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.