USCG USCG Motor
Set 9 • Question #379 of 382
Launch Interactive Practice Room Failure of the feed pump to deliver feedwater to an auxiliary boiler could be caused by_______________.
A
a low pump suction lift
B
abnormally low water temperature
C
grounded probes in the water level control
✓ Correct Answer
D
a high pump suction head
USCG NMC Regulatory Explanation
In USCG Motor Plants (Diesel Engineering), regarding 'Failure of the feed pump to deliver feedwater to an auxiliary boiler could be caused by', the correct operational principle is: 'grounded probes in the water level control'.