USCG USCG Steam
Set 11 • Question #77 of 496
Launch Interactive Practice Room In a properly designed boiler, which of the end points should be reached first?
A
Carryover
B
Circulation
C
Evaporation
D
Combustion
✓ Correct Answer
USCG NMC Regulatory Explanation
In USCG Steam Plants (Boilers & Turbines), regarding 'In a properly designed boiler, which of the end points should be reached first', the verified engineering fact is: 'Combustion'.