Launch Interactive Practice Room When conducting a routine hydrostatic test on a water- tube boiler, you should __________.
A
raise the temperature of the boiler water to 180° F
B
apply hydrostatic pressure equal to the maximum allowable working pressure of the boiler
C
have gags installed on all safety valves
✓ Correct Answer
D
bypass the economizer
USCG NMC Regulatory Explanation
In USCG Steam Plants (Boilers & Turbines), regarding 'When conducting a routine hydrostatic test on a water- tube boiler, you should', the verified engineering fact is: 'have gags installed on all safety valves'.