USCG USCG Steam Set 11 • Question #67 of 496
Launch Interactive Practice Room

When conducting a routine hydrostatic test on a water- tube boiler, you should __________.

A
raise the temperature of the boiler water to 180° F
B
apply hydrostatic pressure equal to the maximum allowable working pressure of the boiler
C
have gags installed on all safety valves ✓ Correct Answer
D
bypass the economizer