Before working on an electric cargo winch master switch or controller, what should be done?
Official USCG Answer & Rule Citation
Correct Answer: Option A — open the circuit breaker in the power supply and tag-out
Safety regulations under 46 CFR Subchapter J mandate opening the supply circuit breaker and applying rigorous lock-out/tag-out (LOTO) procedures prior to servicing any marine electrical controller or winch master switch.