Deck Safety (Supplementary) USCG Question #3393 (Set 6)

The process of waiting a period of time before pretensioning an anchor is known as __________.

Official USCG Answer & Rule Citation

Correct Answer: Option C — soaking

In offshore anchor handling and mooring operations, "soaking" refers to allowing a newly set drag anchor to sit undisturbed in the seabed soil for a designated period before applying full pretension. This allows surrounding sediments to consolidate, enhancing ultimate anchor holding capacity.