Engine General (Supplementary) USCG Question #1513 (Set 27)

When preparing/writing shipyard items for your vessel's upcoming dry docking period, what would you consider as an item regarding CuNi salt water cooling systems/piping?

Official USCG Answer & Rule Citation

Correct Answer: Option A — Identify in your item all steel waster piece pipe spools in the CuNi systems and require them to be removed and replaced.

Under USCG National Maritime Center examination standards, the accepted correct answer is: Identify in your item all steel waster piece pipe spools in the CuNi systems and require them to be removed and replaced..

100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.