When securing the operation of an inert gas system, the final step should be _________.
Official USCG Answer & Rule Citation
Correct Answer: Option C — secure the salt water supply to the scrubber
Securing the salt water supply to the scrubber is the final step to prevent flooding the system or causing backflow into the boiler uptakes. Once the inert gas blower is secured and isolating valves are closed, the water supply must be shut off to maintain system integrity.