Marine Electrical Systems USCG Question #96 (Set 4)

When shore power is being connected to a ship in dry dock, what must be ensured, assuming that the ship's generators are rated at 450 VAC, 60Hz with a total capacity of 5000 kW?

Official USCG Answer & Rule Citation

Correct Answer: Option D — shore power phase sequence must agree with that of the ship

Connecting shore power safely requires strict adherence to phase rotation verification per 46 CFR Subchapter J. If the shore phase sequence does not match the vessel's bus, energizing the system will cause catastrophic reverse-rotation of connected machinery, severe electrical faults, and immediate equipment damage.

100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.
Back to Marine Electrical Systems Sets