Motor Plants & Auxiliary Boilers USCG Question #1360 (Set 27)

Which of the indicator diagrams illustrated indicates the condition that should be corrected by retarding the timing, and the fitting of thicker shims to the connecting rod? Illustration MO-0029

USCG Exam Illustration MO-0029
USCG Examination Diagram: Illustration MO-0029
Official USCG Answer & Rule Citation

Correct Answer: Option D — D

Diagram D exhibits high peak pressures caused by advanced timing combined with reduced clearance volume, requiring both injection retarding and thicker connecting rod shims to lower compression.