Motor Plants & Auxiliary Boilers USCG Question #107 (Set 2)

Which of the routine maintenance procedures listed is required for starting air receivers?

Official USCG Answer & Rule Citation

Correct Answer: Option A — Frequent draining of accumulated moisture.

Under USCG National Maritime Center examination standards, the accepted correct answer is: Frequent draining of accumulated moisture..