Deck General USCG Question #1481 (Set 46)

Who is responsible for the final inspection ensuring a tank barge is provided with the required equipment and has fittings in good and serviceable condition prior to loading cargo?

Official USCG Answer & Rule Citation

Correct Answer: Option D — tankerman or person in charge of loading

The Person in Charge (PIC) or tankerman is legally responsible for verifying the vessel's readiness. Per 46 CFR, they must ensure all cargo equipment, including valves, hoses, and safety fittings, are in good, serviceable condition before commencing transfer to ensure the operation is conducted safely and in compliance with regulations.

100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.
Back to Deck General Sets