USCG USCG General Eng
Set 5 • Question #349 of 498
Launch Interactive Practice Room A major controlling factor in the location of the condensate return piping from a heating system is/are __________.
A
the requirement for a gravity return
✓ Correct Answer
B
the requirement for short laterals run
C
the requirement to minimize conflict with headroom and other services
D
all of the above
USCG NMC Regulatory Explanation
In USCG Marine Engineering General Subjects, for engine room systems involving 'A major controlling factor in the location of the condensate return piping from a heating system is/are', the standard operating requirement is: 'the requirement for a gravity return'.